The Friday Report - August 22, 2014

Posted by admin on August 22, 2014

TMS PRE-PRODUCTION UPDATE 08-22-2014

Wilkinson County:

Halcón Blackstone 4H-2, located roughly halfway between Centreville and Woodville on the south side of Hwy 24. Halcon reported an IP of 553 barrels of oil per day from a reported 10 stage completion with an effective lateral length of 2,853 foot.

Halcón Fassman 9H-1, truck access road is located off Hwy 61 onto Sam Leake Road, then to Whetstone. Drilling complete with a reported 6,030' lateral. Rig moved to Shuckrow. Awaiting fracturing operations.

Halcón Shuckrow 10H-1, located on Sam Leake Road about 5 miles east of Hwy 61, H&P Rig # 623 spudded on July 31.

Halcón S D Smith 1H, located on the Jackson Louisiana Road south of Woodville. H&P Flex 3 Rig# 249 completed a 7,556' lateral in an adjusted drill time of 33 days. A pilot hole was drilled and well logging operations occurred during the rig time on site. Awaiting fracturing operations.

Halcón George Martens 1H, located beside the west side of the south lane of Hwy 61 south of Woodville a couple of miles. H&P Flex 3 Rig #249 on site to drill a planned 7,000' lateral.  Spud 8-8-2014.

Goodrich CMR Foster Creek 24-13, access from Hwy 24 on Hiram McGraw Road to Macedonia Road, then to end of Helmer Road. Nabors Rig # 624 spudded May 30. Rumored fishing issues have slowed progress. I expect this rig to move to the CMR-Foster Creek 8H site when finished.

Goodrich CMR/Foster Creek 31-22H-1, access from Hiram McGraw Road off of Hwy 24. Nabors X-17, Spud July 8. Drill reportedly finished in 35 days or less.  Nabors X-17 moved to Goodrich Verberne 5H-1 well in Tangipahoa Parish. Awaiting fracturing operations.

Sanchez Dry Fork Creek # 2H, drilling completed (again) with a 5,000 foot lateral.  Rapad Rig#31 moving to Amite County St. Davis #1 site located on Kahnville Road south of Gloster, MS.

EnCana Pintard 28H-2, located roughly 3 miles north of Centreville off Macedonia Road- Trinidad Rig # 124 finished drill with 20,807' total depth and an approximate lateral length of 8,500'.  Fracturing reportedly successfully completed earlier this week.  Awaiting plug drill out.

Comstock CMR Foster Creek 28-40 No. 1H, located on Will Floyd Road. Access appears to be south off of Hwy 563 on to Macedonia Road, then on to Netterville Road, then on to Will Floyd Road. Trinidad Rig # 103 began drilling on August 14.

Amite County:

Sanchez St. Davis #1, accessed from Hwy 24 in Gloster, located down Kahnville Road about 6 miles southeast of Gloster. RAPAD Rig # 31 moving on site now. Expect drilling to start next week.

Encana Ash 13H-1 and 13H-2, Located on the east side of Ash Road, accessed via Lower Centreville Road about 3 miles southeast of Centreville. Trinidad Rig # 124 spudded July 21. Both -1 and -2 intermediates should be completed...first lateral should be well underway. If things go as planned, these wells could be completed by the middle of September.

Encana Lyons 35H-2- Located on same site as Lyons 35H-1, Fracturing operations complete on an estimated 5,000 foot lateral. Plug drill out underway.

Encana Sabine 12H-1 and 12H-2, located off of Enterprise Road, south of Hwy 24 about 3 miles out of Liberty, access is from Hwy 48. Trinidad Rig # 125 spudded 12H-1 on June 20 and 12H-2 on June 23. Core sample operations have consumed most of the past three weeks.  Drilling should be started in the first lateral.  Preparations for fracturing already underway.  If things go as planned drilling could be completed on these two wells by middle to late September.

Goodrich Spears 31-6H-1, Located on the recently completed C H Lewis site pad on the west side of Bates School Road north of Gillsburg. Ensign Rig #753, spudded July 22. Drilling in the lateral. Drilling expected to be completed next week.

Goodrich Bates 25-24H-1, located roughly 2 miles northeast of Liberty off of Hwy 569 North. No word on lateral length, but expecting 5,000' or more. Frac operations on 19 planned stages underway.

Goodrich Denkmann 33-28H-2, located in Amite County on the Mississippi/Louisiana line in T1N, R4E. Accessed from the Louisiana side through Weyerhaeuser roads off of Tolar Hurst/Parish Road 181 off of Hwy 1044 north of Hwy 38. Fracturing successfully completed on 22 of 24 stages.

St. Tammany: Permit pending

Washington Parish: Permits pending, site preparation underway.

Tangipahoa: Goodrich Verberne 5H-1, located south of Hwy 38 on Hwy 1061. Nabors X-17 should be drilling soon, if not already.

St. Helena Parish: Comstock pad being prepared...permit pending.

East Feliciana: Permits pending

West Feliciana:

Halcon Walker drill, previously scheduled, has been delayed.

Drama free fracturing operations of late.  That's a good thing.  Lots of good reports out from EnerCom conference this week.

After months of record rainfall, we're still having an occasional afternoon shower, but, for the most part, blue skies and clear sailing seem to represent the current state of the TMS.