Encana's February TMS Fracking Schedule?
As of Friday, Schlumberger had completed 6 and 11 stages of a 19 and 20 stage planned fracking of the Longleaf 29H-1 and -2 wells. With luck these fracks will be finished by the end of next week.
It would appear next up will be the Lawson 25-13H-1, a 10,000' lateral. My guess is a 30 or so stage frack, so let's say 10 days for it.
By then, it would be reasonable to expect the McIntosh/Reese drilling to be completed. Maybe, just maybe, these two wells will be fracked immediately after the Lawson.